Updating latest revision from CVS server

Updating modification from CVS server

  1. Click Update button on Teamwork Toolbar.
    Update from toolbar
    Update from toolbar
  2. Similar to commit, you can review the change and preview the diagram in Update dialog.
    Update dialog
    Update dialog
  3. If there are conflicts, resolve it similar to commit, but the changes will apply to local project instead of commit to server immediately.
  4. Click OK button to update. VP-UML will open the updated project.
    Updated project
    Updated project

Checking status

  1. Open Teamwork Client dialog.
  2. Select the teamwork project in the list.
  3. Select Project > Check Update from menu.
    Update project from menu
    Update project from menu

    Or click Check Update button from toolbar.
    Update project from toolbar
    Update project from toolbar
  4. You can see the status showing Has update or Up-to-date, it also indicate local project status (local project not modified) or (local project modified).
    Project status
    Project status

 

 
5. Resolving conflicts Table of Contents 7. Rolling back undesired changes by reverting changes
 

Product

Try this feature with

Visual Paradigm for UML

Technical Support

Have technical issues or suggestions? Please contact Visual Paradigm Support Team.

Sales Support

Have questions related to registration, licensing or payment? Feel free to contact Visual Paradigm Sales Team.

Discussion Forum

Share your suggestions of opinions at VP Discussion Forum.