PERT Chart Closer Look



       For each task in a PERT chart, specify the task name, which is the name of the work package, by default.
















                        Task Name
                                                    CRM System Integration
                                                                                                              Duration
                        ID
                                                           001                 48 days
                                                                                                              End Date
                        Start Date                    Dec 16, 2016           Feb 02, 2017


                                                                                                       Responsible Person
                                                                     Peter














       • An ID that uniquely identifies the task.
       • The planned start and finish date of the task. Note that a task can only be start if the depending task is completed. In other words the
          start date of a task must be greater than the finish date of all the depending tasks.

       • The duration, which is the number of days between start and end date. And, The person who are responsible for this task.