Page 23 - EA & ISTM for Enterprise
P. 23
Examples of a “REAL” Modeling
From Work Breakdown Modeling to Projects scheduling
1
ArchiSurance
PERT Chart
1 . 1 1 . 2 1 . 3 1 . 4
Unified CRM Back-Office Suite Digital Customer Exp. Doc. Mgmt.
1 . 1 . 1 1 . 2 . 1 1 . 3 . 1 1 . 4 . 1
CRM System Integration Hardware Setup IoT-Based Data Warehousing Doc. Mgmt. Backup Server Setup Database Migration
002 6 days
Jan 4, 2017 Jan 10, 2017
1 . 1 . 2 1 . 2 . 2 1 . 3 . 2
Tim
Database Migration Software Modification Social Media Apps Development
Unified CRM
CRM System Integration Staff Training System Integration Testing
1 . 1 . 3 1 . 2 . 3 001 34 days 004 16 days 005 3 days
System Integration Testing Phasing Out Legacy
Nov 30, 2016 Jan 3, 2017 Jan 4, 2017 Jan 20, 2017 Jan 11, 2017 Jan 14, 2017
John Terry Responsible
1 . 1 . 4 1 . 2 . 4
Staff Training Staff Training
Hardware Setup
006 11 days
Nov 30, 2016 Dec 11, 2016
Morris
Staff Training Phasing out Legacy
008 17 days 009 10 days
Back-Office Suite
Feb 11, 2017 Feb 28, 2017 Feb 11, 2017 Feb 21, 2017
Terry Jamie
Software Modification
007 72 days
Nov 30, 2016 Feb 10, 2017
John
Digital Customer Exp.
IoT-Based Data Warehousing Automated Data Analysis
010 50 days 012 16 days
Feb 22, 2017 Apr 13, 2017 Apr 14, 2017 Apr 30, 2017
Tim Jamie
Social Media Apps Development
010 29 days
Feb 22, 2017 Mar 23, 2017
John
Document Management Doc. Mmt. Backup Server Setup
013 20 days
Apr 14, 2017 May 4, 2017
Morris
23