Project Change Management





 • A change request arises when someone wants a change to the agreed-upon project baseline or deliverables for a        Change Control  Configuration Management Control
    project.


 • It can pertain to project, product, documents, requirements, or any other control items identified and documented
    under the Change and Configuration Management Plan.


 • Upon completion, the request is submitted to the Change Control Board or other similar body for review and
    approval.




















               • In the Planning phase, both the management of Change control and configuration management control have been planned.

               • This phase involves processing the change requests following the procedure planned, documenting the result of the change
                  request review and executing the change, if a request is approved.