Page 12 - IT Project Management Framework - Planning
P. 12

PERT Chart



       For each task in a PERT chart, specify the task name, which is the name of the work package, by default.










                        Task Name

                                                   Support Searching E-Res
                                                                                                              Duration
                        ID
                                                           001                 48 days

                                                                                                              End Date
                        Start Date                    Dec 16, 2016          Feb 02, 2017



                                                                     Peter                             Responsible Person












       • For each task in a PERT chart, specify the task name, which is the name of the work package, by default.

       • An ID that uniquely identifies the task.
       • The planned start and finish date of the task. Note that a task can only be start if the depending task is completed. In other words the
          start date of a task must be greater than the finish date of all the depending tasks.

       • The duration, which is the number of days between start and end date. And, The person who are responsible for this task.

       • And, the person who are responsible for this task.
                                                                                                                                         12
   7   8   9   10   11   12   13   14   15   16   17