Page 13 - IT Project Management Framework - Planning
P. 13
PERT Chart
Support Searching E-Res
Now, you can transfer all the tasks to the Tasker Manager automatically Support Reserving E-Res
Task Manager always in sync with the Gantt View
Amend Vacany Task List Gantt Chart
Week Month
Sun 03-06 - Sat 04-01
ID Title Start Time End Time Sat 03-25 Sun 03-26 Mon 03-27 Tues 03-28 Wed 03-29 Thur 03-30 Fri 03-31 Sat 04-01 Sun 04-0
1 Design Vacancy Editing screen 2017-03-25 2017-03-27 Design Vacancy Editing screen
• The planned start and finish date of the task. Note that a task can only be start if the depending task is completed. In other words the 2 Design vacancy approval pag... 2017-03-25 2017-03-27 Design vacancy approval page (amendment)
3 Implement the vacancy amen... 2017-03-25 2017-04-07 Implement the vacancy amendment logic
start date of a task must be greater than the finish date of all the depending tasks.
4 Implement the vacancy amen... 2017-03-25 2017-03-30 Implement the vacancy amendement approval logic
5 Implement email delivery logic 2017-03-29 2017-04-03 Implement email delivery logic
6 Log the amendment record 2017-04-03 2017-04-06 Log the amend
7 Presents the amendement re... 2017-04-06 2017-04-07
8 Test vacancy editing 2017-04-07 2017-04-10
9 Test vacancy amendment ap... 2017-04-11 2017-04-11
10 Prepare manual on the Vacan... 2017-04-22 2017-04-22